Bridge work almost done

Contractors erect scaffolding at the Leamington side of the historic Victoria Bridge. Photo: Mary Anne Gill.

Painting and maintenance work on the $2.6 million Victoria ‘High Level’ Bridge project is expected to be finished next month, weeks earlier than expected.

Scaffolding reached the southern end of the bridge late last week and crews are now working from the Leamington riverbank toward the centre.

More than 2000 litres of paint is being used on the project with 7000 scaffolding components. The bridge has been scaffolded and repainted in sections starting on the Cambridge town side earlier this year.

Contractors reached the halfway point last month and faced the trickiest part of the bridge works.

Scaffolding was completely suspended from the bridge deck, and they had to be careful of weight and other factors.

Asset Management team leader Paul Strange said on top of the ‘business-as-usual’ work to prepare, sandblast, maintain and repaint the bridge, contractors also carried out some additional concrete work to tidy up the bridge’s foundations on the Cambridge side.

The hinged truss bridge over the Waikato River was prefabricated in 1906 by the American Bridge Company of New York.

The bridge, a Heritage New Zealand Category One structure, was shipped to New Zealand as a 330-tonne kitset and taken by train to Cambridge and Te Awamutu for erection on either side of the Waikato River.

It was the first example of construction using the process of cantilevering the two half arches from each bank.

The use of lattice steel in bridges was relatively common in the latter half of the 19th century. In New Zealand, it was used in railway bridges like the central North Island Hāpuawhenua and Taonui viaducts and the High Level Bridge. It was also used for the Eiffel Tower in Paris.

See: High-level paint job

See: Future proofing the bridge

Contractors erect scaffolding at the Leamington side of the historic Victoria Bridge. Photo: Mary Anne Gill.

 

More Recent News

Councils prepare for water decision

Ōtorohanga District Council will debate the future of the district’s water services delivery model at an extraordinary council meeting on April 8, after receiving financial data in the next few weeks. Ōtorohanga councillors will decide…

Paewira backers object to costs

Global Contracting Solutions has filed an objection with Waipā District Council against the cost of its resource consent application to build a waste to energy plant in Te Awamutu. The application will be heard by…

Eco expo a success

Youngsters from around the region enjoyed four hours of fun activities last Saturday at Te Awamutu Museum’s Tui & Tama Eco Expo. The Ecology Expo was the third held as part of the museum’s Tui…

Roundabout solution proposed

A figure of eight shaped roundabout is being suggested for drivers turning into Matangi Rd from Morrinsville Rd – State Highway 26. Hamilton City Council has presented an elongated roundabout which would include both the…